Taiwan Says Nuclear Water Still Leaking Inside Power Plant

Taiwanese authorities said a water leak that began 3 1/2 years ago inside a state-owned atomic power plant is yet to be halted, as lawmakers debate whether to put the island’s nuclear future to an island-wide vote.

About 19.8 liters (5.2 gallons) has been collected from two leaking used-fuel pools inside Taiwan Power Co.’s No. 1 plant in the period, according to a report from the state oversight body, the Control Yuan. The Ministry of Economic Affairs was faulted for failing to properly supervise the utility, the report shows.