Blackstone Finishes Germany’s Biggest Offshore Wind Farm

(Corrects last paragraph of story first published April 4 to show Meerwind is among biggest offshore wind plants.)

Blackstone Group LP (BX) said it finished building its 1.2 billion-euro ($1.7 billion) wind farm in the German North Sea.

WindMW GmbH, a joint company of Blackstone and Windland Energieerzeugungs GmbH, installed the last of 80 wind turbines of the 288-megawatt Meerwind Sued I Ost project near Helgoland yesterday, the developer said today in an e-mailed statement.

Grid operator TenneT TSO GmbH promised the plant can be connected to the land-based electric network and start operating this year, Brigita Jeroncic, a spokeswoman for WindMW, said by phone.

Meerwind will be one of Germany’s largest offshore wind-energy plants, capable of supplying 360,000 homes. The project in 2011 was financed by Banco Santander SA (SAN) of Spain, Lloyds Banking Group Plc and Denmark’s export credit agency EKF, with KfW Group and Commerzbank AG included in the total of nine lenders.

To contact the reporter on this story: Stefan Nicola in Berlin at snicola2@bloomberg.net

To contact the editors responsible for this story: Reed Landberg at landberg@bloomberg.net Alex Devine

Press spacebar to pause and continue. Press esc to stop.

Bloomberg reserves the right to remove comments but is under no obligation to do so, or to explain individual moderation decisions.

Please enable JavaScript to view the comments powered by Disqus.