Kinross Gold to Start Next Expansion Study at Tasiast Mine

Kinross Gold Corp. (K), Canada’s third- largest gold miner, will start a feasibility study on expanding its Tasiast mine in Mauritania with a 38,000 ton-per-day mill.

A plant that size will “provide optimum economics” for the mine, Toronto-based Kinross said today in a statement, citing a preliminary study. The company expects to complete the feasibility study in the first quarter of 2014, after which it will decide whether to finish the engineering work and begin construction on the expansion.

“The decision to proceed will be based on a number of considerations, such as energy supply, operating costs, capital costs and of course the gold price,” Chief Executive Officer J. Paul Rollinson said today on a conference call. “We’ve got a lot of gold in the ground and we have a lot of options.”

Kinross acquired Tasiast as part of its C$8 billion ($7.9 billion) purchase of Red Back Mining Inc. in 2010. The company said in February it took a $3.09 billion writedown on the project after it scaled back an expansion plan and mining- industry capital and operating costs increased. Tasiast currently has a processing capacity of 8,000 tons a day, the company said.

Rollinson, who replaced Tye Burt as Kinross’s CEO in August, is seeking to lower production costs and improve spending discipline. The company forecasts 2013 capital spending will drop to $1.6 billion from $1.92 billion last year.

Comparing Options

“The priority for us is balance sheet strength and we are going to keep the balance sheet strong,” Rollinson said today.

Kinross originally planned to build a 60,000-ton-per-day ore-processing mill at Tasiast, and in February said it was no longer considering that option.

The company said in August it was studying a 30,000-ton project to compare the economics.

The pre-feasibility study announced today showed that under the 30,000-ton scenario, so-called all-in sustaining costs at Tasiast would be $735 an ounce of gold with average annual gold output 830,000 ounces in the first five years of production.

The initial capital cost for the project at that size was estimated at $2.7 billion, Kinross said today. Kinross assumed a gold price of $1,500 an ounce of gold in calculating the project economics and $1,200 for designing the mine pit.

Barrick Gold Corp. (ABX) and Goldcorp Inc. (G) are the largest Canadian gold miners by sales.

Kinross fell 2.2 percent to C$5.44 at 9:49 a.m. in Toronto. The shares have dropped 44 percent this year.

To contact the reporters on this story: Liezel Hill in Toronto at lhill30@bloomberg.net; Thomas Biesheuvel in London at tbiesheuvel@bloomberg.net

To contact the editor responsible for this story: Simon Casey at scasey4@bloomberg.net