Exelon Byron 2 Refueling Sinks Midwestern Nuclear Output

Exelon Corp. (EXC) began a refueling shutdown at the 1,136-megawatt Byron 2 reactor in Illinois, sending Midwestern nuclear-power production to the lowest level in almost a year.

Nationwide generation retreated 2.6 percent from yesterday to 78,077 megawatts, or 77 percent of capacity, the biggest drop in eight weeks, according to U.S. Nuclear Regulatory Commission data compiled by Bloomberg. Output was 0.2 percent higher than one year ago with 20 of 104 reactors offline.

Byron 2, about 85 miles (137 kilometers) west of Chicago, halted for scheduled refueling and maintenance after operating at 100 percent of capacity yesterday, according to Paul Dempsey, an Exelon spokesman based at the plant.

The shuttered unit led the decline in Midwestern output, which fell 6.4 percent to 15,750 megawatts, the lowest level since April 22, according to commission data compiled by Bloomberg.

Reactor maintenance shutdowns, usually undertaken in the U.S. spring or fall, when energy use is at its lowest, may increase consumption of natural gas and coal to generate electricity. The average refueling down time was 46 days in 2012, according to the Nuclear Energy Institute.

To contact the reporter on this story: Christine Harvey in New York at charvey32@bloomberg.net

To contact the editor responsible for this story: Dan Stets at dstets@bloomberg.net

Press spacebar to pause and continue. Press esc to stop.

Bloomberg reserves the right to remove comments but is under no obligation to do so, or to explain individual moderation decisions.

Please enable JavaScript to view the comments powered by Disqus.