Southern Pacific Concludes Strategic Review Process

FOR: Southern Pacific Resource Corp. 
AUGUST 21, 2014 
Southern Pacific Concludes Strategic Review Process 
CALGARY, ALBERTA--(Marketwired - Aug. 21, 2014) - Southern Pacific Resource
Corp. ("Southern Pacific" or the "Company") (TSX:STP) has
concluded its strategic review process.  
On December 11, 2013 Southern Pacific announced the initiation of a strategic
review process ("SRP") aimed at identifying and considering all
strategic and financial alternatives available to the Company. The SRP was
initiated after realization that the original 12 well pairs drilled at the
STP-McKay Thermal Project were unlikely to fill the process facility to its
design capacity of 12,000 bbl/d and that additional workovers on the existing
pairs as well as the addition of new well pairs would likely be required. RBC
Capital Markets were retained as a strategic advisor to Southern Pacific's
Board of Directors throughout the SRP. In March 2014, as part of the SRP, the
Company completed the addition of a new first lien debt facility, replacing the
then existing facility which improved Southern Pacific's current
liquidity. The consideration of other strategic alternatives aimed at
maximizing stakeholder value was also fully explored. During the SRP, proposals
were received and the SRP was extended longer than expected in order to fully
explore the proposals. However, it was determined by the Company's Board
of Directors that none of the proposals received were acceptable and it was
further concluded that the current best alternative for all stakeholders is to
continue with the development of the Company's existing assets, initially
focused on increasing production rates at STP-McKay. 
With the strategic process concluded, Southern Pacific has reduced its number
of employees to reflect a narrower focus but will be staffed appropriately to
continue its base of operations and near-term development. The immediate
development plan will be to continue with workovers aimed at improving
productivity from the SAGD well pairs at STP-McKay. In 2014, to date, Southern
Pacific has successfully completed three workovers on its SAGD well pairs at
STP-McKay, which involved the installation of inflow control devices
("ICDs") into the existing producers of the well pairs (refer to
press releases dated March 17 and June 17, 2014). The ICD system is intended to
improve wellbore conformance in a two part process. First, the horizontal
producer length is segmented with isolation packers and second, the ICD devices
are installed into the segments and are designed to restrict the inflow of
steam from reservoir short circuits, thus promoting conformance in other
sections of the wellbore. This allows production to occur with less rate
restriction on the entire well pair. The success of these ICDs is apparent as
data is collected. To date, the Company has been pleased with the performance
of the ICDs and with the configurations installed, has been able to improve
well bore conformance and operate the well pairs with a reduced risk of steam
short circuits damaging wellbore integrity. In aggregate, these three
installations have improved oil rates by over 60% to date (the three ICD
installed well pairs produced 870 bbl/d in total for July) as compared to the
rates prior to each installation. It is expected these wells will continue to
improve over time as conformance and steam chambers are developed. The Company
will now be installing additional ICDs into several additional well pairs in
the field. A service rig has been moved on site and will remain on site for
approximately eight weeks and will install ICDs into four well pairs and a
steam splitter into the injector of a fifth well pair. All of the planned
workovers affect well pairs that have been rate restricted or shut-in
throughout the SRP, in order to manage steam short circuits and protect the
well pairs integrity prior to running the ICDs. With the completion of these
installations, the Company will have installed ICDs into seven of its 12 well
pairs. Pending results from those installations, an additional three well pairs
may be equipped with ICDs later in the year. There are two well pairs that are
not expected to require ICD installations in order to improve conformance; one
has developed good conformance without ICDs and the other well pair will have a
steam splitter installed in the injector as the method to improve conformance. 
Southern Pacific also has received regulatory approval to downspace the
existing McKay well pads with additional SAGD well pairs. As mentioned in the
Company's December 11, 2013 press release, the Company believes additional
well pairs will be required in order to fully utilize the available steam
capacity at the STP-McKay Thermal Project. Southern Pacific believes the most
prudent strategy is to add them between the existing well pairs, which were
originally spaced 100 m apart, allowing ample room for additional well pairs to
be drilled. Southern Pacific filed its application with the Alberta Energy
Regulator ("AER") to downspace Pads 101 and 102 in February 2014 and
received approval in July 2014. The total Pad 102 downspace project cost is
estimated at $51 million. This project's timing has also been affected by
the Company's SRP. A revised timing estimate of first steam to the
downspaced wells on Pad 102 would be mid 2015 or later, and this is dependent
upon the Company obtaining sufficient liquidity to proceed with this project. 
At STP-Senlac, the Company has full regulatory approval to drill the next pad
of three well pairs, Phase L, at an estimated remaining cost of $18.8 million.
The timing of initiating this project has also been delayed as a result of the
SRP and the timing of the drilling will be dependent upon confirming the
results of the ICD installations at STP-McKay as increasing volumes at
STP-McKay is the near term focus for the Company. If the ICD results are as
expected, and with approvals in place, Phase L drilling could commence on short
notice, but the final timing has not been determined.  
In July, production for STP-McKay averaged 2,064 bbl/d. At Senlac, July's
production averaged 1,612 bbl/d. The Company's estimated working capital
as of June 30 is $34 million. The Corporate year-end financial statements are
scheduled for release during the last week of September 2014.  
The Company is also announcing the resignation of Mr. Mike O'Krancy (Vice
President, Projects) and the retirement of Mr. Ron Clarke (Chief Operating
Officer), effective September 1, 2014. Southern Pacific would like to thank
them for their efforts and contributions over the past several years, and
wishes them well in their future endeavors. Additionally, Mr. Ward Mallabone
has elected to step down as a Director of the Board. The Company would like to
thank Mr. Mallabone for his guidance and direction over the past eight years.  
About Southern Pacific  
Southern Pacific Resource Corp. is engaged in the exploration, development and
production of in-situ oil sands in Alberta's Athabasca region, and the
thermal production of heavy oil in Senlac, Saskatchewan. Southern Pacific
trades on the TSX under the symbol "STP."  
This news release contains certain "forward-looking information"
within the meaning of such statements under applicable securities law including
but not limited to: the timing of installation of additional ICDs on well
pairs, the estimated cost and timing of the Pad 102 downspace project, and the
estimated cost for drilling Phase L at STP-Senlac.  
Forward-looking information is frequently characterized by words such as
"plan", "expect", "project", "intend",
"believe", "anticipate", "estimate",
"may", "will", "potential", "proposed"
and other similar words, or statements that certain events or conditions
"may" or "will" occur. These statements are only
predictions. Forward-looking information is based on the opinions and estimates
of management at the date the statements are made, and are subject to a variety
of risks and uncertainties and other factors that could cause actual events or
results to differ materially from those projected in the forward-looking
statements. These factors include, but are not limited to the inherent risks
involved in the exploration and development of oil and gas properties and of
oil sands properties, Southern Pacific's ability to obtain additional
liquidity to commence or continue with planned projects, conformance
acceleration techniques, delays in ramp-up operations, the uncertainties
involved in interpreting drilling results and other geological data,
fluctuating oil prices and discounts, the possibility of unanticipated costs
and expenses, uncertainties relating to the availability and costs of financing
needed in the future and other factors including unforeseen delays. As an oil
sands enterprise in the development stage, Southern Pacific faces risks
including those associated with exploration, development, ramp-up, approvals
and the continuing ability to access sufficient capital from external sources
if required. Actual timelines associated may vary from those anticipated in
this news release and such variations may be material. Industry related risks
could include, but are not limited to, operational risks in exploration,
development and production, delays or changes in plans, risks associated to the
uncertainty of reserve estimates, health and safety risks and the uncertainty
of estimates and projections of production, costs and expenses. For a
description of the risks and uncertainties facing Southern Pacific and its
business and affairs, readers should refer to Southern Pacific's most
recent Annual Information Form. Southern Pacific undertakes no obligation to
update forward-looking statements if circumstances or management's
estimates or opinions should change, unless required by law.  
The impact of any one risk, uncertainty or factor on a particular
forward-looking statement is not determinable with certainty as the factors are
interdependent, and the Board's and management's future course of
action would depend on its assessment of all information at the time.  
The reader is cautioned not to place undue reliance on this forward-looking
Southern Pacific Resource Corp.
Byron Lutes
President & CEO
Southern Pacific Resource Corp.
Howard Bolinger
INDUSTRY:  Energy and Utilities - Oil and Gas  
-0- Aug/21/2014 13:00 GMT