VANCOUVER, March 25, 2014 /CNW/ - Copper Mountain Mining Corporation (TSX: 
CUM) (the "Company" or "Copper Mountain") announces that construction of the 
new permanent secondary crusher at the Copper Mountain mine located in 
southern British Columbia continues to move forward as planned and on 
schedule.  Purchase orders for all of the major mechanical and electrical 
components have been placed.  The main components of the crusher have arrived 
in Canada and have been transported via rail to Kamloops, BC where they are 
being prepared for transportation by a specialized truck to the mine site.  
The lower bowl assembly is the largest component piece of the crusher and 
weighs over 100 tonnes.  Due to its size and weight special road permits were 
provided by the Department of Transportation in a timely manner to meet the 
schedule for the highway transportation to the mine site. These permits were 
received early last week and the lower bowl assembly has now been transported 
to the mine site.  The Company engaged Nickel Bros Heavy Lifting and 
Transportation to complete this leg of the transportation which entailed 
closing the main highway between Kamloops and Princeton in 20km sections as 
the convoy moved down the road.  It took four nights to make the 200 kilometer 
trip, because the transportation had to occur between midnight and 5 am each 
night to minimize traffic disruptions along the route. 
This crusher will be the largest cone crusher installed in western Canada and 
has the ability to crush the 6 inch rock from the primary crusher down to 2 
inches in size. The new crushing facility is designed to operate at a rate of 
2,800 tpoh and is designed to meet the most demanding and high tonnage 
applications.  Foundation work for the Crusher Slab is complete and it is 
being prepared for placement of the newly arrived lower bowl assembly.  Once 
the lower bowl assembly is installed, building contractors will be mobilized 
to start the building erection. Following the building erection, the new 
conveyor system installation will commence in the spring time.  The total cost 
of construction for the secondary crusher facility is estimated to be $40 
million and construction is expected to be completed by mid-summer.  Once 
installed, 100% of the mill feed will be sized to the 2 inch range, which will 
allow the mill to operate consistently at or above design capacity rates of 
35,000 tpd. 
The short term mitigating measures implemented in 2013 to increase mill 
throughput continue to be successful with January and February's operational 
results being in line with the production expectations. 
About Copper Mountain Mining Corporation:
Copper Mountain's flagship asset is the Copper Mountain mine located in 
southern British Columbia near the town of Princeton. The Company has a 
strategic alliance with Mitsubishi Materials Corporation who owns 25% of the 
mine. The Copper Mountain mine commenced production in the summer of 2011 and 
has continued to improve its operations since startup. The 18,000 acre site 
has a large resource of copper that remains open laterally and at depth. The 
mine has significant exploration potential that will need to be explored over 
the next few years to fully appreciate the properties full development 
potential.  Additional information is available on the Company's web site at 
On behalf of the Board of
"Jim O'Rourke" 
Jim O'Rourke, P.Eng.
Chief Executive Officer 
Note:  This release contains forward-looking statements that involve risks and 
uncertainties.  These statements may differ materially from actual future 
events or results.  Readers are referred to the documents, filed by the 
Company on SEDAR at, specifically the most recent reports which 
identify important risk factors that could cause actual results to differ from 
those contained in the forward-looking statements.  The Company undertakes no 
obligation to review or confirm analysts' expectations or estimates or to 
release publicly any revisions to any forward-looking statement

SOURCE  Copper Mountain Mining Corporation 
Galina Meleger, Corporate Communications 604-682-2992 ext.224 Email:Galina or Rod Shier, Chief Financial Officer 604-682-2992 ext.222 
PDF available at: 
To view this news release in HTML formatting, please use the following URL: 
CO: Copper Mountain Mining Corporation
ST: British Columbia
-0- Mar/25/2014 12:00 GMT
Press spacebar to pause and continue. Press esc to stop.