Sunshine Oilsands Ltd.: Update on West Ells Project Capital Cost Estimate and Construction Schedule

Sunshine Oilsands Ltd.: Update on West Ells Project Capital Cost Estimate and 
Construction Schedule 
This is an announcement made pursuant to the Inside Information Provisions 
under Part XIVA of the Securities and Futures Ordinance (Cap. 571) and Rule 
13.09 of the Rules Governing the Listing of Securities on the Stock Exchange. 
HONG KONG, April 22, 2013 /CNW/ - Sunshine Oilsands Ltd. ("Sunshine") (HKEX: 
2012; TSX: SUO) has undertaken a detailed review of its cost estimate and 
schedule for the West Ells SAGD Project, currently under construction near Ft. 
McMurray, Alberta. The installed cost for the Project was previously estimated 
at approximately $468 million, excluding contingencies and $30 million for the 
shared, multi-project main access road, with first steam scheduled for the 
third quarter of 2013. 
While good progress and important milestones have been achieved on the 
Project, several factors have contributed to an assessment that the West Ells 
project will see minor delays and higher costs. Sunshine now expects Phase 1 
first steam to be injected in late Q3 or early Q4. 
Total (Phase 1 and 2) direct costs at West Ells are now estimated at 
approximately $496 million, excluding the road and further contingencies. This 
new figure is based on our revised cost and presentation format, with certain 
expenditure items now allocated out to other areas of investment or cost 
categories. 
The Project's current status for selected areas of activity is summarized as: 


    --  Drilling of the first eight well pairs for the 5,000 bpd Phase
        1 is now complete, with well completions underway. The drilling
        rig will now move to the second well pad required for the
        additional 5,000 bpd Phase 2, scheduled to be brought on line
        in the first quarter of 2014.
    --  Approximately 75% of the piles have been set for Phase 1, with
        Phase 1 piling expected to be completed by the end of May.
    --  Module procurement is well underway, with 5 modules completed
        and the balance of Phase 1 modules under construction.
    --  Field constructed storage tanks are 60% complete.
    --  About 80% of the operations team has been hired and is expected
        to move to the site over the next two months to assist with
        facility turnover, commissioning and start up.

With the currently anticipated cost increases, and after allowing for 
expenditures for costs and investments in other categories of activity, 
Sunshine forecasts its 2013 overall capital needs to grow by approximately $30 
million.  This estimate assumes certain investments relating to development of 
future projects will be deferred if necessary.  Overall funding for 2013 and 
2014 will continue to come from a combination of cash on hand, borrowing, and 
potential joint ventures, as well as revenue from early stage production from 
West Ells in 2014. Sunshine intends to use the Company's revolving credit 
facility of up to $200 million as a source of funding, with availability and 
size subject to meeting certain tests. Sunshine has notified its lending group 
of the increased capital cost at West Ells.  The Company continues to monitor 
markets to optimize its sources of funding.

ABOUT SUNSHINE OILSANDS LTD.

Sunshine Oilsands Ltd. is one of the largest non-partnered holders of oil 
sands leases by area in the Athabasca oil sands region, which is located in 
the province of Alberta, Canada. Since the Company's incorporation on 22 
February 2007, Sunshine has secured over one million acres of oil sands leases 
(equal to approximately 7% of all granted leases in this area).

The Company's principal operations are the exploration, development and 
production of its diverse portfolio of oil sands leases. Its principal 
operating regions in the Athabasca area are at West Ells, Thickwood, Legend 
Lake, Harper, Muskwa, Goffer, Pelican and Portage. Sunshine's oil sands leases 
are grouped into three main asset categories: clastics, carbonates and 
conventional heavy oil.

FORWARD-LOOKING INFORMATION AND DISCLAIMER

This announcement may contain forward-looking information that is subject to 
various risks, uncertainties and other factors. All statements other than 
statements and information of historical fact are forward-looking statements. 
The use of any words "estimate", "forecast", "expect", "project", "plan", 
"target", "vision", "goal", "outlook", "may", "will", "should", "believe", 
"intend", "anticipate", "potential", and similar expressions are intended to 
identify forward-looking statements. Forward-looking statements are based on 
Sunshine's experience, current beliefs, assumptions, information and 
perception of historical trends available to Sunshine, and are subject to a 
variety of risks and uncertainties including, but not limited to those 
associated with resource definition and expected reserves and contingent and 
prospective resources estimates, unanticipated costs and expenses, regulatory 
approval, fluctuating oil and gas prices, expected future production, the 
ability to access sufficient capital to finance future development and credit 
risks, changes in Alberta's regulatory framework, including changes to 
regulatory approval process and land-use designations, royalty, tax, 
environmental, greenhouse gas, carbon and other laws or regulations and the 
impact thereof and the costs associated with compliance. Although Sunshine 
believes that the expectations represented by such forward-looking statements 
are reasonable, there can be no assurance that such expectations will prove to 
be correct. Readers are cautioned that the assumptions and factors discussed 
in this information release are not exhaustive and readers are not to place 
undue reliance on forward-looking statements as our actual results may differ 
materially from those expressed or implied. Sunshine disclaims any intention 
or obligation to update or revise any forward-looking statements as a result 
of new information, future events or otherwise, subsequent to the date of this 
announcement, except as required under applicable securities legislation. The 
forward-looking statements speak only as of the date of this announcement and 
are expressly qualified by these cautionary statements. Readers are cautioned 
that the foregoing lists are not exhaustive and are made as at the date 
hereof. For a full discussion of our material risk factors, see "Risk Factors" 
in our most recent Annual Information Form, "Risk Management" in our current 
MD&A and risk factors described in other documents we file from time to time 
with securities regulatory authorities, all of which are available on the Hong 
Kong Stock Exchange at www.hkexnews.hk, on the SEDAR website at www.sedar.com 
or our website at www.sunshineoilsands.com.

This document does not constitute and is not an offer to sell or a 
solicitation of an offer to buy common shares of the Company in the United 
States (including its territories and possessions, any State of the United 
States and the District of Columbia) or elsewhere.

Sunshine Oilsands Ltd., Mr. John Zahary, President & CEO, Mr. David Sealock, 
Executive VP, Corporate Operations, (1) 403 984 1446, 
investorrelations@sunshineoilsands.com, www.sunshineoilsands.com

http://www.hkexnews.hk

http://www.sunshineoilsands.com

http://www.sedar.com

SOURCE: Sunshine Oilsands Ltd.

To view this news release in HTML formatting, please use the following URL: 
http://www.newswire.ca/en/releases/archive/April2013/22/c7368.html

CO: Sunshine Oilsands Ltd.
NI: OIL UTI FIN 

-0- Apr/22/2013 13:08 GMT


 
Press spacebar to pause and continue. Press esc to stop.