Songa Offshore SE : Songa Offshore SE : Songa Trym delayed

          Songa Offshore SE : Songa Offshore SE : Songa Trym delayed

Due to unexpected mechanical failures to already overhauled, installed and
certified equipment and late delivery of OEM equipment, the completion of the
yard stay for Songa Trym will be further delayed. The work and acceptance
testing is now anticipated to be completed during the second half of February.

Until the work is completed, it is difficult to give an accurate figure
regarding the cost implication of the delay, but the additional time,
personnel and repair costs are expected to increase the costs compared to the
previously communicated estimates.

Once the additional work and client acceptance testing is completed, Statoil
will undertake aplanned project to upgrade the mud systems on the rig. This
will take place at the current location at Stand-by rate and the rig will
thereafter enter into its 3+2 year contract with Statoil under direct Songa
Offshore management.

4 February 2013
Limassol, Cyprus

This information is subject of the disclosure requirements pursuant to section
5-12 of the Norwegian Securities Trading Act.

------------------------------------------------------------------------------

This announcement is distributed by Thomson Reuters on behalf of Thomson
Reuters clients.

The owner of this announcement warrants that:
(i) the releases contained herein are protected by copyright and other
applicable laws; and
(ii) they are solely responsible for the content, accuracy and originality of
the
information contained therein.

Source: Songa Offshore SE via Thomson Reuters ONE
HUG#1675396
 
Press spacebar to pause and continue. Press esc to stop.