Sunshine Oilsands to Release Its 2012 Third Quarter Results

HONG KONG, Nov. 13, 2012 /CNW/ - Sunshine Oilsands Ltd. (the "Corporation" or 
"Sunshine", HK: 2012) today is pleased to announce its unaudited interim 
financial results for the three and nine month periods ended September 30, 
2012. All figures are in Canadian dollars unless otherwise stated. Please see 
the attached announcement for further information. 
Highlights 
Operational Update - Third Quarter of 2012: 
Sunshine is a major holder and developer of oil sands resources, with 
approximately 70 billion barrels of total Petroleum Initially In Place 
("PIIP"). The Corporation is focused on development of these assets with the 
first phase of a 10,000 barrels per day project, currently under construction 
at West Ells, scheduled for start up in mid 2013. Sunshine is also progressing 
regulatory approvals for two additional 10,000 barrels per day (total 20,000 
barrels per day) projects at Thickwood and Legend Lake. Approvals are expected 
in the first half of 2013. With over 4.96 billion barrels of contingent 
resources and 445 million barrels of proved plus probable ("2P") reserves, the 
Corporation has significant commercial development potential. In addition, 
Sunshine has recently updated its commercial development plans in the West 
Ells, Thickwood and Legend Lake areas and is now targeting over 300,000 
barrels per day of production from these areas, representing a 50% increase in 
previously announced commercial production targets. 
West Ells Development 
As of September 30, 2012, $110.9 million has been incurred for West Ells 
equipment, engineering, construction, civil works, drilling, completions and 
other project related expenditures. The Project is currently on schedule and 
on budget for completion. The Corporation estimates total capital investment 
for its West Ells 100,000 barrels project to approximate $3.5 billion. 
Sunshine remains focused on West Ells Phase One construction, which has an 
initial production rate of 5,000 barrels per day, followed by an already 
approved expansion to the planned production capacity of 10,000 barrels per 
day. First steam is expected to commence in mid-2013 and first production is 
expected in the fourth quarter of 2013. 
The access road to West Ells is now complete and ready for heavy hauls. This 
will ensure that project milestones are met and that the project will be 
completed on schedule for first steam in mid 2013. Subsequent to quarter end, 
on October 10, 2012, pilings for the Central Process Facility ("CPF") 
commenced. As well, some of the major equipment, including a gas turbine 
generator and an evaporator was in transit to marshalling yards. Other major 
equipment still to be received includes steam generators, free water knockout, 
pumps, and heat exchangers. Civil construction of the CPF is approximately 40% 
finished, with facilities general engineering approximately 75% complete. 
In addition to the road and CPF, the first of Well Pad 2 SAGD well pairs 
spudded on October 29, 2012. The camp is fully functional, and the borrow pits 
are complete and in use. For capital commitments, 100% of the long lead 
equipment has been ordered and approximately 80% of the secondary long lead 
equipment has been procured. Phase 1 downhole completion and production 
equipment have been ordered and drilling rigs arrived on August 20, 2012. 
Drilling rigs for the observation wells were mobilized and were spudded on 
October 26, 2012. No major delays have been encountered. 
Thickwood and Legend Lake 
In addition to the progress made on the 10,000 barrel per day project 
applications approvals for both the Thickwood and Legend Lake projects, the 
Corporation has progressed the Front End Engineering and Design ("FEED") for 
Thickwood. This work is approximately 10% complete. In addition, detailed 
baseline environmental data collection is ongoing and is expected to be 
completed by the end of 2012. This work provides information required for 
project applications larger than 12,000 barrels per day in anticipation of 
future commercial development plans. 
Cold flow assets 
The Corporation continues with the exploration and development of its Muskwa 
heavy oil assets. As at September 30, 2012, five pads with 39 development 
wells have produced a cumulative total of approximately 305,000 barrels. 
Muskwa cumulative production for the first 9 months of 2012 is barrels 
approximately 168,000, representing an average of 625 barrels per day. The 
Corporation continued production optimization activities in the Muskwa field 
by implementing new technologies and techniques for enhancing production, sand 
clean out and other types of wellbore stimulations. The Corporation also 
commenced construction of its planned pad extension to accommodate future 
drilling. The Corporation received regulatory approval to install electric 
heaters on two horizontal wellbores at its Muskwa operations. Field work 
commenced late in the summer and is scheduled to be completed in mid-fourth 
quarter of 2012. Muskwa remains in the resource definition stage for the 
Corporation's financial reporting purposes. As a result, the Corporation 
capitalizes all costs incurred to date including operating costs net of 
revenues. 
The Board of Directors of the Corporation is pleased to announce the results 
of the Corporation and its wholly-owned subsidiaries for the three and nine 
month periods ended September 30, 2012 together with comparative figures for 
the corresponding period in 2011 as follows: 
President's Message to Shareholders 
We are pleased to present to you the unaudited interim financial results 
including the interim financial statements and management's discussion and 
analysis of Sunshine Oilsands Ltd. ("Sunshine") for the three and nine months 
ended September 30, 2012. This report presents a discussion of key highlights 
for the first nine months of 2012, a performance update, summary comments on 
developments and our 2013 outlook. 
We would like to extend our sincere gratitude to you, our shareholders, for 
your continued support and interest in Sunshine. At Sunshine, we believe we 
have the assets and experience to continue to pursue significant value-added 
opportunities. We continue to focus on executing milestone undertakings in the 
West Ells project area, where first steam is scheduled for mid-2013. West Ells 
has an initial production target rate of 5,000 barrels per day, which will be 
followed by an approved expansion to a planned production capacity of 10,000 
barrels per day. In addition to West Ells activities, Sunshine is progressing 
regulatory approvals for two additional 10,000 barrels per day projects, one 
in Thickwood and one in Legend Lake. 
Operational Review 
At the start of the third quarter, we released the results of our updated 
independently prepared Reserves and Resource Reports (the "Reserves and 
Resource Reports"). These reports, dated May 31, 2012, were prepared by GLJ 
Petroleum Consultants Ltd. and DeGolyer and MacNaughton Canada Limited and the 
results confirmed a substantial increase in our recognized reserves and 
resources base. 
Main highlights of the independently prepared Reserves and Resource Reports 
include the following: 


    --  69 billion barrels of Total Petroleum Initially In Place
        ("PIIP"),
    --  5 billion barrels of Best Estimate Contingent Resources with an
        aggregate pre-tax PV10% value of $6.9 billion (increase of 1.9
        billion barrels representing 63% growth);
    --  80 million barrels of proved ("1P") reserves with an aggregate
        pre-tax PV10% value of $312 million (increase of 78 million
        barrels);
    --  445 million barrels of proved plus probable ("2P") reserves
        with an aggregate pre-tax PV10% value of $918 million (increase
        of 26 million barrels); and
    --  603 million barrels of proved plus probable plus possible
        ("3P") reserves with an aggregate pre-tax PV10% of $1.6 billion
        (increase of 42 million barrels).

The Reserves and Resources Reports confirmed significant increases in PIIP and 
Best Estimate Contingent Resource recognition in both the clastics and 
carbonates categories. PIIP recognition increased by approximately 24 billion 
barrels to approximately 69 billion barrels. Clastics Best Estimate Contingent 
Resource recognition increased by 1.2 billion barrels to 3.6 billion barrels 
primarily due to the Corporation's drilling program in its core areas of 
Harper, Opportunity and Pelican Lake. Carbonates Best Estimate Contingent 
Resource recognition increased in the core areas of Goffer, Muskwa and 
Portage, adding over 700 million barrels. Based on this, our current share 
price is trading at a significant discount to our PV10% resource and reserves 
value. At a 10% discount rate for 2P and Best Estimate Contingent Resource 
before taxes, this equates to approximately HK$21.40 per share.

During the third quarter, development of our first phase Steam Assisted 
Gravity Drainage ("SAGD") project at West Ells progressed well. Activities 
throughout the summer and increasing through the fall period continued to 
advance construction and development at the West Ells site. The access road 
was completed as were the borrow pits. Our camp is now fully functional. 
Pilings for the Central Process Facility commenced on October 10, 2012. In 
addition, following quarter end, some of the major equipment was in transit to 
marshalling yards. Drilling rigs for the observation wells were mobilized and 
our first SAGD well pair was spudded subsequent to quarter end on October 29, 
2012. No major delays have been encountered in our planned West Ells 
construction schedule.

Thickwood and Legend Lake continue to advance through the regulatory process 
with approvals currently expected by mid-2013 for an initial10,000 barrels per 
day of production in each area.

Financial Review

The successful completion of the initial public offering ("IPO") on March 1, 
2012 and the Listing on the Stock Exchange of Hong Kong Limited have been 
significant achievements. Sunshine raised gross proceeds of HK$4.5 billion 
(approximately $570 million) and secured significant investments from 
cornerstone investors. With this financing, we secured a financial platform 
that validates our business intent to develop our large oil sands asset base.

Subsequent to the end of the third quarter, the Corporation successfully 
secured a $200 million credit facility with a syndicate of financial 
institutions, led by Alberta Treasury Branches and Bank of China (Canada). 
This oversubscribed facility was expanded from its original size due to strong 
support from financial institutions that included Bank of America N.A., Canada 
Branch, HSBC Bank Canada, Morgan Stanley Senior Funding, Inc., Scotiabank, 
Toronto-Dominion Bank, UBS AG Canada Branch and Industrial and Commercial Bank 
of China (Canada). This credit facility positions the Corporation well to 
complete construction of the West Ells project, to fund front end costs of the 
Thickwood project and to advance program and regulatory development to expand 
capacity for the West Ells, Thickwood and Legend Lake projects.

During September, the Corporation commenced a share buyback program that ran 
from September 16 to October 12, 2012. During that time, the Corporation 
repurchased approximately 61 million shares. Sunshine continues with an active 
investor relations effort throughout Asia, North America and globally. We 
continue to emphasize the attractiveness of the Corporation's value in 
communications with existing shareholders and with potential new shareholders. 
In order to increase the incentive for North American shareholders to buy our 
stock, we applied and obtained conditional approval to list our Class "A" 
common voting shares on the Toronto Stock Exchange.

Joint Venture Initiatives

Joint venture discussions continued during the third quarter. We are pleased 
to confirm that we are continuing to work with Sinopec International Petroleum 
Exploration and Production Corporation, with whom we have a Memorandum of 
Understanding for strategic cooperation, as well as other parties who have 
expressed interest for involvement in our development of our attractive 
assets. We look forward to reporting details of matured joint venture 
discussions in a timely manner.

Corporate Review

The Corporation consistently maintains a disciplined approach in health, 
safety and environmental issues and remains committed to operating in a 
socially responsible manner with regularly conducted emergency response 
training, and safety and environmental audits of our operating facilities. We 
had no significant incidents to report during the third quarter of 2012.

Sunshine also remains committed to working with local stakeholders as we build 
an organization that is intended to be meaningful in a global context.

Strategic Positioning

Sunshine has recently updated its commercial development plans in the West 
Ells, Thickwood and Legend Lake areas and is now targeting over 300,000 
barrels per day of production from these areas, representing a 50% increase in 
previously announced commercial production targets.

With approximately 70 billion barrels of PIIP, Sunshine has a significant 
presence in the north-western part of the Athabasca oil sands region that 
represents an opportunity for investors seeking value growth. Our outlook for 
the remainder of 2012 and looking ahead to 2013 is one of significant promise. 
With over 4.96 billion barrels of contingent resources and 445 million barrels 
of 2P reserves, Sunshine has significant commercial development potential with 
considerable upside. We are confident that our internal development and 
evaluation efforts complemented with broadening the market's understanding of 
Sunshine's assets, will result in share price appreciation over time. We 
continue to work towards first steam at West Ells by mid-2013. Production from 
West Ells will provide immediate cash flows to re-invest in our other planned 
capital projects, Thickwood and Legend Lake. This should, combined with 
anticipated expansion applications and approvals for our projects, increase 
probable and proved reserves, which are typically ascribed to higher values in 
active markets.

Sunshine has achieved several milestones during the first nine months of 2012. 
These would not have been possible without the committed efforts of our Board 
of Directors and our dedicated, hard-working employees. We will continue to 
seek out and attract talented people to sustain a high level of excellence in 
execution of our corporate development plans. We believe in the immense 
potential of our asset base and understand that to increase shareholder value, 
we need to remain disciplined and focused on project milestones and within our 
financial means. We look forward to a busy winter season and are excited by 
the potential of our planned development projects.

John Zahary  President and Chief Executive Officer  November 14, 2012

About Sunshine Oilsands Ltd.

Sunshine Oilsands Ltd. is one of the largest non-partnered holders of oil 
sands leases by area in the Athabasca oil sands region, which is located in 
the province of Alberta, Canada. Since the Company's incorporation on 22 
February 2007, Sunshine has secured over 464,897 hectares (1,148,785 acres) of 
oil sands leases (equal to approximately 7% of all granted leases in this 
area).

The Company's principal operations are the exploration, development and 
production of its diverse portfolio of oil sands leases. Its principal 
operating regions in the Athabasca area are at West Ells, Thickwood, Legend 
Lake, Harper, Muskwa, Goffer, Pelican and Portage. Sunshine's oil sands leases 
are grouped into three main asset categories: clastics, carbonates and 
conventional heavy oil.

For further enquiries, please contact:

Sunshine Oilsands Ltd.



Mr. John  Mr. David Sealock
Zahary

President Executive VP, Corporate Operations
& CEO



Tel: +1-403-984-1446

Email:
investorrelations@sunshineoilsands.com

Website: www.sunshineoilsands.com

http://www.sunshineoilsands.com

SOURCE: Sunshine Oilsands Ltd.

To view this news release in HTML formatting, please use the following URL: 
http://www.newswire.ca/en/releases/archive/November2012/13/c7801.html

CO: Sunshine Oilsands Ltd.
NI: FIN OIL UTI MNG ERN 

-0- Nov/14/2012 02:24 GMT


 
Press spacebar to pause and continue. Press esc to stop.